VIRS PRODUCT & SUBMITTAL LEAD TIMES
Last Updated: June 17th 2022
Note:
We will have no PE Stamping available From June 20th until June 30th 2022.
We will be closed in Markham July 1st 2022 for Canada Day
& We will be closed in Nashville & Reno July 4th 2022 for Independence Day
We are having supply issues with some Springs, Molded Rubber Elements & Powder Coating.
COVID-19 Delivery Schedule Disclaimer: The specified delivery time is only preliminary and Swegon reserves the right to postpone the delivery date if the reason for this, is directly or indirectly, caused by COVID-19 pandemic.
VIBRATION ISOLATION & RESTRAINT SYSTEMS
Product | Scope (QTY) | Lead Time | ||
---|---|---|---|---|
Stock Isolation | Std. | QS1 | QS2 | |
FS (SA, 1A, 2A, 3A) FST (SA, 1A, 2A, 3A) | ≤12 | 5 | 3 | N/A |
13–30 | 7 | 4 | 3 | |
31–50 | 10 | 7 | ||
>50 | ||||
FST-4A Nashville plant only | ≤12 | 5 | 3 | N/A |
CM (1S, 2S, SN, 1N, 2N) | ≤6 | 5 | ||
Any | ||||
CSR-H (1A,2A,3A) | ≤12 | 5 | 3 | N/A |
13-24 | 7 | 4 | ||
>24 | N/A | N/A | ||
GW-38,50,63 | <700 | 3 | 48 hrs. | 24 hrs. |
700-1500 | 7 | |||
>1500 | ||||
SFS (SA,1A,2A, 2N) | <12 | 5 | 3 | N/A |
12–20 | 7 | 4 | ||
20–50 | 10 | 7 | ||
>50 | ||||
SH/SHB/SHR/SHRB SHC/SHCB/SHCH 4" Deflection Nashville ONLY | <30 | 5 | 3 | N/A |
30–100 | 7 | 4 | ||
>100 | ||||
SH-1SS Nashville plant only | <12 | 10 | 3 | N/A |
12-20 | 14 | 4 | ||
>20 | N/A | N/A | ||
NH-1 | <50 | 3 | N/A | N/A |
50-100 | 7 | 4 | ||
>100 | ||||
NH-2 | <50 | 5 | 3 | N/A |
50 - 150 | 7 | 4 | ||
150 - 500 | 10 | 7 | ||
>500 | ||||
NHC/NHCH | <30 | 5 | 3 | N/A |
30–100 | 7 | 4 | ||
>100 | ||||
RD (1, 2, 3, 4) | Any | |||
SRD (1,2) | <12 | 5 | 3 | N/A |
12–20 | 7 | 4 | 3 | |
20–30 | 10 | 7 | ||
>30 | ||||
NP [Cut sizes (2×2, 4×4, 6×6, etc.)] N [Cut sizes (2×2, 4×4, 6×6, etc.)] | ≤200 | 5 | 3 | N/A |
<200 | N/A | |||
NP (Full sheet) | ≤20 | 3 | 48 hrs. | 24 hrs. |
>20 | ||||
N (Full sheet) | ≤10 | 3 | 48 hrs. | 24 hrs. |
>10 | ||||
FN (Full Sheet) | ≤20 | 3 | 48 hrs. | 24 hrs. |
>20 | ||||
SIPS 125 (1.5 to 8) SIPS 125 NP (1.5 to 8) | <6 | 3 | 48 hrs. | 24 hrs. |
6–12 | 10 | 7 | 4 | |
>12 | ||||
SIPS 250 (1.5 to 8 ) SIPS 250 NP (1.5 to 8 ) SIPS (10 to 16) SIPS-NP (10 to 16) Low Profile SIPS (10 to 16) Nashville plant only | ≤6 | 6 wks. | N/A | |
>6 | 7 wks. | N/A | ||
SRK (25) | ≤60 | 5 | 3 | 48 hrs. |
>60 | . | |||
BB-13 | <200 | 3 | 48 hrs. | 24 hrs. |
200-400 | 7 | 4 | 48 hrs. | |
>400 | ||||
BB-19 | <20 | N/A | N/A | |
>50 | N/A | N/A | ||
BBR 13-50 | <200 | 3 | 48 hrs. | 24 hrs. |
200-400 | 7 | 4 | 48 hrs. | |
>400 | ||||
BBR 19-63 | <50 | 5 | 3 | 24 hrs. |
50-100 | 7 | 4 | 48 hrs. | |
>100 | ||||
BBR-13-63, 13-88, 19-88 | Any | |||
DAB (6 and 12) | ≤20 | 5 | 3 | 48 hrs. |
>20 | ||||
BC-50 | <100 | 3 | 48 hrs. | 24 hrs. |
100-300 | 7 | 4 | 48 hrs. | |
>300 | ||||
Cable | Any | |||
RRK | Any | |||
VAC-1, -2 | <500 | 3 | 48 hrs. | 24 hrs. |
500-1000 | 10 | 7 | 3 | |
>1000 | ||||
Seismic Stop Washers | Any | 5 | 3 | 48 hrs. |
SPS/SPSA | ≤20 | 5 | 3 | 48 hrs. |
>20 | ||||
SRB | ≤50 | 3 | 48 hrs | 24 hrs |
>50 | ||||
SCSR-H (-1A, -2A) (hot-dip galvanized) | <12 | 5 | 3 | |
12-24 | 10 | 7 | ||
>24 | ||||
SCSR-H (-1A, -2A) (oversized base plate & hot-dip-galvanized) | <6 | 5 | 3 | N/A |
6-10 | 10 | 7 | ||
>10 | ||||
SCSR-H-(3A) (hot-dip-galvanized & with or without oversized base plate) | <6 | 8 | 5 | 3 |
6-10 | 13 | 9 | ||
>10 | ||||
SCSR-H (4A) (hot-dip-galvanized & with or without oversized base plate) Nashville plant only | <6 | 8 | 5 | |
6-10 | 13 | 9 | ||
>10 | ||||
SCSR-Q(-1A, -2A, -3A) *Only Available from Nashville *Oversize Base Plate and Tapped Top Plate Models Available | ≤10 | 5 weeks | N/A | N/A |
>10 | N/A | N/A | ||
QC-38, 50 | <50 | 3 | 48 hrs. | 24 hrs. |
50-100 | 5 | |||
>100 | N/A | |||
QC-63, 75 ( QC-63 Discontinued limited stock remains) | All | N/A | N/A | |
Anchors (KB-TZ, KH-EZ, Dewalt SD1) | Any | 10 | ||
Anchors (Custom) | Any | |||
** Manual orders of standard products, available on V-A Express add an additional 48 hours for order entry **NOTES 1. Lead times reflect working days 2. All product lead times start aging after written confirmation of release 3. Use the longest lead time when quoting multiple product types 4. QSI = 25% premium, QS2 = 50% premium 5. Must confirm with factory in writing before Quickships are accepted 6. PO release must be received within 48 hours of written approval of Quickship 7. Reno operates Monday to Thursday only |
||||
CURBS & RAILS
Standard Curbs & Rails
Product | Scope (QTY) | Lead Time | |
---|---|---|---|
VCR Curbs (Standard) | 10 | 5 wks. | |
ARTR Rails (Standard) | 10 | 6 wks. | |
FSR Type-1 (Galvanized) & FSR Type-2 (Prime Painted) | ≤2 | 6 wks. | |
3-4 | 7 wks. | ||
>4 |
Non-Standard Curbs & Rails
BASES
Limited Quick Ships, Please Contact Factory for Availability.
Product | Scope (QTY) | Lead Time | ||
---|---|---|---|---|
Stock Isolation | Std. | QS1 | QS2 | |
CIB/ TCIB/ LCIB | <8 | 6 wks. | N/A | N/A |
9-16 | 7 wks. | N/A | N/A | |
>16 | ||||
CIB 6/CIB 8 (Pre-configured Inertia Bases) | <8 | 5 wks. | N/A | N/A |
9-16 | 6 wks. | N/A | N/A | |
>16 | ||||
IFB | ≤5 | 6 wks. | N/A | N/A |
>5 | 7 wks. | N/A | N/A | |
CIB (for generator sets or air handling units) | ≤2 | 7 wks. | N/A | N/A |
>2 | N/A | N/A | ||
Lead Time Adders for Bases | Special Finish | N/A | N/A | |
Motor Slide Rail Support | Add 7 days | N/A | N/A | |
Oversized Bases (>7'x12') | Add 7 days | N/A | N/A | |
Non-Standard Customization | N/A | N/A |
Bases - Cooling Tower Bases (CTB)
Product | Scope (QTY) | Lead Time | ||
---|---|---|---|---|
Stock Isolation | Std. | QS1 | QS2 | |
CTB (hot-dip galvanized) | <2 and <25' x 25' ea. | 6 wks. | N/A | N/A |
2< qty <4 and <25' x 25' ea. | 7 wks. | N/A | N/A | |
Other | ||||
CTB -TYPE-3 (hot-dip galvanized) Nashville only | <2 | 8 wks | N/A | N/A |
2< qty <4 and <25' x 25' ea. | N/A | N/A | ||
CTB -TYPE-3 (hot-dip galvanized) Reno only | Any | N/A | N/A | |
CTB (prime painted) | <2 and <25' x 25' ea. | 6 wks. | N/A | N/A |
2< qty <4 and <25' x 25' ea. | 7 wks. | N/A | N/A |
FLEXIBLE CONNECTORS
Flexible Connectors
Product | Lead Time | |
---|---|---|
QS1 | QS2 | |
Rubber or Metal Bellows Expansion Joints | ||
Braided Metal Flexible Connectors | ||
Spider Guides | ||
Seismic V-Loops | ||
Thermal Expansion Compensators | ||
Externally Pressurized Expansion Joints |
PIPE GUIDE & ANCHORS
Pipe Guide & Anchors
Product | Scope (QTY) | Lead Time | ||
---|---|---|---|---|
Stock Isolation | Standard | QS1 | QS2 | |
PRA (25, 38, 50) | <10 | 10 days | ||
≥10 | Not Applicable | Not Applicable | ||
PRA (63) | Any | Not Applicable | Not Applicable | |
PRA-S (25, 38, 50, 63 ) | Any | |||
PRA-T (25, 38) | <10 | 10 days | ||
≥10 | ||||
PRA-ST (25, 38) | Any | Not Applicable | Not Applicable | |
PRG (25) | <10 | 10 days | ||
≥10 | ||||
PRG (38) | Any | Not Applicable | Not Applicable | |
PRG-S(25,38) | Any | Not Applicable | Not Applicable | |
Spider Guides | Any | Not Applicable | Not Applicable | |
NOTES 1. All product lead times start aging after written confirmation of release 2. Use the longest lead time when quoting multiple product types 3. QSI = 25% premium, QS2 = 50% premium 4. Must confirm with factory in writing before Quickships are accepted 5. PO release must be received within 48 hours of written approval of Quickship |
FLOATING FLOORS
Floating Floors
Product | Lead Time | ||
---|---|---|---|
Floating Floors - Standard material supply only | 6 wks. | ||
Floating Floors - Standard material supply and installation within the Greater Toronto Area | 7 wks. |
SUBMITTALS
Vibration Isolation & Restraint Systems Submittals
Type | |||
---|---|---|---|
Non-Seismic | Scope (QTY) | Lead Time | RSLT |
Isolation Selection (# of Equipment) (Ex. CSR selection for cooling towers) | 4 | 5 | 5 |
12 | 7 | ||
24 | 8 | ||
48 | 9 | ||
Spring Hangers (# of SHs estimated) | 10 | 6 | 5 |
20 | 8 | ||
40 | 10 | ||
60 | 12 | ||
Inertia Bases (# of bases) CIB, TCIB, LCIB | 4 | 5 | 5 |
8 | 7 | ||
12 | 8 | ||
Steel Bases (# of bases) IFB, CTB | 4 | 10 | 5 |
8 | 12 | ||
12 | 14 | ||
Custom VIRS | Any | 8 | |
NOTES 1. Lead times reflect working days 2. All submittals lead times start aging after receipt of required information. See Appendix A. 3. Resubmittal lead times start aging after receipt of a revised purchase order (if changes result in added costs) 4. Use the longest lead time when quoting multiple submittal types 5. QS1 = 25% premium, QS2 = 50% premium 6. Must confirm with factory in writing before Quickships are accepted 7. PO release must be received within 48 hours of written approval of Quickship |
Type | |||||
---|---|---|---|---|---|
Seismic | Scope (QTY) | Lead Time | QS1 | QS2 | RSLT |
Seismic/Wind Overturn Calculations (# of Equipment) | 2 | 7 | 4 | 3 | 5 |
8 | 9 | 6 | 4 | ||
14 | 13 | 8 | 5 | ||
20 | 17 | 10 | 6 | ||
Seismic Inertia Bases (# of bases) CIB, TCIB, LCIB | 4 | 7 | 4 | 3 | 5 |
8 | 9 | 6 | 4 | ||
12 | 13 | 8 | 5 | ||
Seismic Steel Bases (# of bases) IFB, CTB | 4 | 10 | 7 | 4 | 5 |
8 | 12 | 8 | 5 | ||
12 | 14 | 9 | 6 | ||
Seismic Markup (Ductwork, Piping, Cable Trays) (# of Drawings) (Mechanical Room Drawing - 4 Drawings) | 2 | 7 | 4 | 3 | 5 |
4 | 8 | 5 | 3 | ||
8 | 10 | 7 | 4 | ||
16 | 14 | 9 | 6 | ||
24 | 18 | 11 | 7 | ||
Risers (Seismic) *Identical Supply and Return Count as 1 Riser | 2 | 8 | N/A | N/A | 6 |
6 | 12 | N/A | N/A | 6 | |
>6 | N/A | N/A | 6 | ||
Risers (Non-Seismic) *Identical Supply and Return Count as 1 Riser | 2 | 6 | N/A | N/A | 6 |
6 | 10 | N/A | N/A | 6 | |
>6 | N/A | N/A | 6 | ||
NOTES 1. Lead times reflect working days 2. All submittals lead times start aging after receipt of required information. See Appendix A. 3. Resubmittal lead times start aging after receipt of a revised purchase order (if changes result in added costs) 4. Use the longest lead time when quoting multiple submittal types 5. QS1 = 25% premium, QS2 = 50% premium 6. Must confirm with factory in writing before Quickships are accepted 7. PO release must be received within 48 hours of written approval of Quickship |
Curb & Rails Submittals
Floating Floor Submittals
Product | Scope | Lead Time | |||
---|---|---|---|---|---|
QS1 | QS2 | RSLT | |||
Floating Floors | 1 | 8 | 5 | 3 | 5 |
2 | 11 | 7 | 5 | ||
>2 | |||||
NOTES 1. Lead times reflect working days 2. All submittals lead times start aging after receipt of required information. See Appendix A. 3. Resubmittal lead times start aging after receipt of a revised purchase order (if changes result in added costs) 4. Use the longest lead time when quoting multiple submittal types 5. QS1 = 25% premium, QS2 = 50% premium 6. Must confirm with factory in writing before Quickships are accepted 7. PO release must be received within 48 hours of written approval of Quickship |
APPENDIX
Required information for the Approval Drawings (Seismic and/or Wind Calculations):
Equipment:
- Equipment drawings including all dimension (not required for suspended equipment)
- Equipment weight: Corner weights are required otherwise total weight will be distributed evenly
- Location of the equipment (1st floor, roof, etc.).
- Hanging locations for suspended equipment: If they are more than 2 or 4 points
- Structure Type: Floor, Ceiling and walls (Concrete, Metal Decking, Structural Steel, etc.)
- The size of the equipment base (Rail, Flat at the bottom, etc.), if it’s applicable.
Piping/Ductwork:
- Construction drawings or the latest set of drawings showing all sizes
- Trapezed or single hung for piping
- Coordination drawings for the vertical piping/ductwork in the mechanical room
- Determining the area that ductwork/piping is supported using vibration isolators (if there is any)
- Details of the duct supports (c/w all dimension) if the duct is floor/roof mounted
- Locations and details of flex connectors (if there is any)
- Sheet Metal Thickness for the ductwork (if it’s not 18 ga)
Spring Hangers for Piping/Ductwork:
- Plan and elevation drawings (or 3D drawings) showing all drops and risers
- Hanging location is a must to calculate the weight at the hanging point for spring selection